- Parallel run extension by one month, between March 11, 2011 – May 20, 2011.
- Mandatory upgrade for direct market data users.
- New port and bundle information required.
- Contact Omega support via email to request bundles for new ITCH feed.
Considering feedback from Omega’s subscribers, we have decided to extend the production parallel run
phase by one month, from March 11 – April 18, to March 11 – May 20. We feel this will better allow our subscribers sufficient time to transition between the two market data feeds. Please note, this is a mandatory upgrade, and direct market data users who do not cutover by May 20th will no longer have access to market data.
For users looking to upgrade to the new market data feed in both GTE and Production, new ports and bundles will be required. Please contact Omega Support to request the new information.
Important Dates
• February 28, 2011 | New ITCH feed available for testing in Test environment. |
• March 11, 2011 | Parallel run begins, new ITCH available in our Production environment. |
• May 20, 2011 | Cutover to new ITCH complete, and old feed retired. |